September 5, 2019 Minutes
10 Present
April 4, 2019 Minutes approved
- Treasures Report:
- Treasures report was unavailable t the September meeting.
- All outstanding bills are paid to date.
- Trails:
- New signs have been ordered.
- S55 trail reroute in Clyde from 414 to Brown Rd needs to have new bridge covered. Suggested to try horse mat material.
- Need to work on steel bridge to install on Savannah trail and move RR ties from Red Creek to Savannah.
- Have 2-year DOT permit for culvert at Rt 21 in Marion. Cannot start until the end of September. Need excavator.
- Groomers:
- We will run 2 groomers this year and need to coordinate and schedule operators
- Lockers are ordered for the tucker and will install soon.
- Move the tucker to Adams garage to install lockers and clean it up for rust proofing.
- Groomer Barn:
- The Groomer Barn Committee will insulate and complete electric service after rear door is installed. Once time is established will need volunteers to help.
- Door is ready to go and will be installed by Martin Overhead door for free.
- $1300 has been approved to purchase the door.
- Miscellaneous:
- Wallington fire department is looking to possible do a fund raiser with us in the future.
- Ted has been working on the 501c3. Should be able to complete once he gets a copy of the current club bylaws
- We may do another Poker Run this year
-
This topic was modified 4 years, 11 months ago by Snowman.